Graphic stating Improvements in West BromwichWork has started on an essential project in West Bromwich.

The scheme will see a total of 50 metres of water main replaced across Spon Lane South into Hackett Drive, resulting in the highest water quality and a reliable water supply to customers. 

Where and when?

The work will carried out for about two weeks starting 19 January 2021.

Will traffic be affected?

Traffic should  not be affected as no traffic management is required

Will this affect my water supply?

Your supply will not be affected but we will give you advanced warning if there will be any interruptions.


We are committed to investing in new water mains, to reduce leakage by at least 15% and to ensure our customers continue to receive a reliable and high-quality water supply.


Updates

27 January 2021

Due to a Lane closure required on Spon Lane, the work will continue on Sunday and we hope to install the new main from Spon Lane South through to the junction of Hackett Drive.

Our customers supply will not be affected as they will be supplied by a temporary overland pipe however, once the new main has passed the quality check through sample results, advanced warning will be given to enable the final connection.


Posted: 27 January 2021